New production area
We are expanding our production area in Duisburg, Germany to 720 m2. Then we are prepared to satisfy more efficiently the growing customer demand.
Construction progress:
Agost 2010: Roof and indoor work.
July 2010: Instalation of the walls.
June 2010: Instalation of the metalic construction.
May 2010: Preparation of the metalic construction.
March 2010: Concrete is now firmed up.
February 2010: At the moment is the foundation done and the beam construction is in process.
Here some pictures of the expansion work progress:
| Agost 2010 | |
![]() |
![]() |
| July 2010 | |
![]() |
![]() |
| June 2010 | |
![]() |
![]() |
![]() |
![]() |
| May 2010 | |
![]() |
![]() |
| March 2010 | |
![]() |
![]() |
| February 2010 | |
![]() |
![]() |
![]() |
![]() |